Thursday, June 24, 2010
Week 12, 25th June
Monday, June 21, 2010
Week 12, 23rd & 24th June
Week 12, 21st & 22nd June
Purchasing procedure is also explained to us so that we have the clear idea of how a stock is purchased.
Week 11, 18th June
Friday, June 18, 2010
Week11, 17th June
Week 11, 16th June
For the electrolysis process, the seawater booster pump will pump the seawater to the strainer for filter purpose. The seawater then will undergo the electrolysis process and the gas hydrogen will stored in the degasifier tank.
Week 11, 15th June
The cation exchanger and anion exchanger needed to regen every 350m3 of usage while mixed bed exchanger is every 4500m3
The regeneration of the anion exchangers requires caustic soda (sodium hydroxide). During the regeneration, warm sodium hydroxide at 50’C is required; hence the regeneration water heater is used to supply demineralized water at 82’C to the water blender which provides 50’C water to the caustic dilution.
The regeneration of the cation exchangers requires sulfuric acid. The supply of 98% sulfuric acid is stored in demineralizer sulfuric acid storage tanks.
Week 11, 14th June
Firstly, service water is fed to the carbon filter. The influent water is passed through a column of activated carbon to remove the major part of the organic matter and residual chlorine.
Then, the water is routed to the cation exchanger packed with a column of strong acid cation, exchange ion resin in the hydrogen form.
The cation effluent is then passed through a strong base anion inside the anion exchanger. The hydrogen ions from the cation resin neutralized the hydroxide ions from the anion resins and yield pure water.
The demineralized water is then passed to the mixed bed exchanger which contain a mixture of anion exchanger and cation exchanger to further polish the water before the water is discharged to demineralized water storage tank.
Week 10, 11st June
In the evening, there is a knowledge sharing session conduct by Amer (mechanical technician). He shared his experience about overhauling shutoff gas valve with us. This work will be done once a year during the outage session. Before installing the valve, they need to measure the valve can sustain how much pressure. The minimum pressure is about 25bar.
Week 10, 10th June
The heart of Voiths’ hydrodynamic torque converter is its hydraulic circuit; consisting of a pump, turbine, and a guide wheel with adjustable guide vanes. This is combined in a common housing filled with hydraulic oil.
The mechanical energy of the motor is converted into hydraulic energy through the pump wheel. In the turbine wheel the same hydraulic energy is converted back into mechanical energy and transmitted to the gas turbine/generator shaft.
The adjustable vanes of the guide wheel regulate the mass flow in the circuit. At closed guide vanes (small mass flow) the power transmission is at its minimum. With the guide vanes completely open (large mass flow), the power transmission is at its maximum.
Week 10, 9thJune
The process of purging stop when the turbine speed drops to 9% of the full speed. The function of purging is to drain out all the combustable gas from combustion compartment until exhaust compartment.
The process of firing starts after the purging until the turbine speed reach full speed.
Turbine speed trend
Week 10, 7th@8th June
Vision – The group envisions itself to be a global player in the energy and energy related business.
Mission – the group’s mission is to enhance shareholder return.
For the Quality Policy & Objective of the plant, the group is committed to be efficient and responsible by ensuring high standards in Quality and achieve full customer’s satisfaction by making ‘Quality A Way of Life’.
Week 9, 4th June
From Nooter Eriksen Operating manual, I learnt that recirculation pump on HP and LP economizers are use to increase the inlet feedwater temperature. It is required during the distillate oil as fuel. Condensation of acid can occur and corrodes the tubes of economizer if the temperature is low.
Week 9, 3rd June
Week 9, 2nd June
Week 9, 1st June
I participated in the steam turbine auxiliaries weekly changeover. As last week I followed patrolman, this week I will be at control center room monitor the changeover. Abang Azmi, SBO, let me to handle the changeover work under his supervise. I need to communicate with Nazirin (BO) to make sure that every pump is function able when I activate the standby pump. Once the pump is running, then the running pump will be deactivated. This process is repeated for every changeover pump.
Week 9, 31st May
I followed abang Fadzli, patrolman to do the gas turbine auxiliaries changeover. Before the changeover begins, abang Fadzli take down the suction pressure discharge pressure abd the expansion tank level for cooling water pump. After the changeover, the readings also need to take down. The following changeover is continuing with turbine compartment ventilation fan and distillate forward pump.
Then, abang Fadzli brought us to activate online water wash to decrease the turbine temperature so that the load will increase.
Week 8, 27th May
Abang Azmin is doing the EDG test run
Thursday, May 27, 2010
Week 8, 26th May
Abang Nasir, peronda, brings me to fire fighting pump house to check the availability of the pump. He explained that if pressure is less than 9 bar, jockey pump is activated while less than 7 bar, electric pump is on. Diesel pump 1 will activate when pressure less than 5 bar and diesel 2 will activate when pressure less than 4 bar.
The procedure of doing the checking is opened the bypass valve to let the water flowing back to water tank. Then manually turn on the electric pump, follow by diesel 1 pump and diesel 2 pump.
Week 8, 25th May
I followed abang Suhaimi, block operator, to do the pump changeover at STG. The pumps that need to do the changeover are demin water transfer pump, closed cycle circulating water pump, service water pump, condenser extraction pump, gland steam condenser exhauster, hydraulic pump, lube oil pump and seawater booster pump.
This activity will be done weekly so that the pump can extend its working period. The main reason is to test the standby pump availability so that when in emergency, it is still functional.
Week 8, 24th May
At around 11am, steam turbine trip suddenly due to loss of instrument pressure. Abang Halim, shift charge engineer (SCE), informed National Load Dispatch Center (NLDC) due to full block trip. Then, he informed ECNI technician to identify the problem. After checking the tube of instrument air that found no leaking, they focus on the air compressor. It is found that the instrument air compressor 1B air separator broken.
After identify the problem, the start up of GT1 begin then ST and GT2. At around 5pm, the SCE declare to NLDC that load back to maximum that is 322MW.
The instrument air compressor 1B that make the steam turbine tripped due to loss of pressure
Wednesday, May 26, 2010
outage, 15th May
After shutdown, the maintenance outage is started. The preventative maintenance that I followed were carbon brush inspection, field breaker maintenance, 52G inspection, exciter inspection, interposing relay panel inspection, protection relay inspection and testing of all DC motors for GT1 , GT2 and ST. as the time is limited, a;; the inspection need to finish it as soon as possible.
For the corrective maintenance, abang Fadzli and abang Razak changed the defect contactor for circulating water pump panel box.
For the plant improvement, the plant had hired the contractor to upgrade the primary injection of 190 feeder PT and CT and the overcurrent and earth fault relays for station board 2. These works are all included in electrical section works.
For the mechanical parts, I participated in the circulating water pump rotary drum screen pit preventative maintenance. A stop block pathway is put to prevent the seawater flow into the drum screen pit. The cleaning process begins with pull up the primary drum screen and cleans it. Then the pit contractor will climb down the pit to clean up the trashes that sink in the pit.
Week 7, 21st May
Week 7, 20th May
Week7, 19th May
In the evening, there is a farewell party for our plant station manager, Mr. Chew, as he is going oversea on June for working purpose.
Week 7, 18th May
Then, abang Munir explained to us that the function of the service air and instrument air and their differences. He also explained the flow of how dry, oil-free compressed air is produce.
The service air system provides compressed air at the required pressure and capacity for general plant use and as a backup supply to the instrument air system while instrument air system provides dry compressed air at the required pressure and capacity for all pneumatic valves, controls, transmitters, and instrument.
Week 7, 17th May
Today work is about corrective maintenance. At the water treatment plant, the demineralized recycle pump 2A is found leaking. I followed abang Ramli to do the checking and rectify it.
In the evening, all the technicians do the cleaning at the workshop as the outage had finished.
Week 6, 14th May
Then all the following works today are just preparation for the outage.
Week 6, 13rd May
En. Rahimi doing the welding for boiler feed pump control valve pipe
For other technicians, they were busy preparing the equipment that need to use during the outage that is on Saturday.
Week 6, 12th May
The contractors are cleaning the primary drum screen
En. Rahimi explained to us the alignment and its function. It is about finding the rotational center of motor and positioning of the motor. The symptoms of misalignment are high discharge of temperature, vibrate or loosen of the foundation bolts and etc. The causes of misalignment are bent shaft, soft foot and etc.
To show us in the more practical way, En. Rahimi brought an old pump to workshop for alignment demonstration. Laser alignment device is used to detect the state of accuracy of the alignment
Week 6, 11st May
Then for the part of the valve, we opened it and do the cleaning as there are a lot of rusted layers in the valve. After finish the cleaning, abang Yunizar then changed the motor oil to let the motor run smoothly.
Week 6, 10th May
The PM that I followed is HRSG blowdown transfer pump. The function of the transfer pump is transferring the demineralized water to water treatment system. Most of the work is about corrosion. The corrosion layers were scraped and the whole exterior of transfer pump was painted with anti-rust paint.
The worker take out the transfer pump using forklift
The exterior of transfer pump was painted with anti-rust paint
Week 5, 7th May
After finish the PM, all the CNI technician went to the boiler building to install the motorized actuator.
Abang Azim is installing the motorized actuator at boiler drum
Week 5, 6th May
Then, abang Syahrul and abang Azim explained briefly about bailey infinet and termination unit in the network system of the power plant. Every process control unit (PCU) will connect to a single termination unit (TU) and send to redundant/bailey infinet communication system. The information then will send to the operator interface station (OIS) to let the operator to control the final control element (open or close, start or stop). For amending the program of the PCU, the programmer can go to the management command system (MSC) or engineering work station (EWS).
Week 5, 5th May
In the evening, I followed abang Syahrul to do the HRSG1 Siemens Continuous emission monitoring system (CEMS) inspection. We need to check the lamp, switch, indication bulbs whether it is function or not. Then, we need to take the measurement for UTM120 and UTM130 device for the flow rate and percentage of oxygen.
Week 5, 4th May
In the evening, En. Sharif asked me to help the electrical section to wash the motor of the air compressor. I used the chemical (synthetic isoporaffinic hydrocarbon) to clean the stains on the shaft of the motor.
The technicains clean the stains on the motor
Week 5, 3rd May
In the evening, Sri Daran gave us a set of basic electrical test. Our result will know after he finish marking the paper.
Sunday, May 9, 2010
Week 4, 30th April
For the visual inspection, we need to check the cleanliness and physical connection of tubing and cables.
For the current measurement status, we need to note down the sample pressure, un-normalized value and superior (dry) current value.
For the calibration process, manually run STREAM 4 and STREAM 1. Then view the chromatography for STREAM 4. There are 7 peak values for chrom-1 and 5 peak values for chrom-2.
For the calibration result on STREAM 4, we need to note down all the components value in the gas. The components are ethane, propane, carbon dioxide, methane and etc.
In the evening, all of the staffs required to attend the knowledge sharing session. En. Azizul, IT executive, provide a talk about the new ICT password policy. It is stated that the password must be changed after 6 months or 180 days of usage. Then, it is the turn for En. Sharif, supervisor for electrical department, gives a talk about steam turbine power distribution system.
Week 4, 29th April
In the evening, I was given an assignment by Sri Daran. I need to find out the ANSI code for the protection relay that used in the plant. ANSI stand for America National Standard Institution that provide the code for all the protection relay.
Week 4, 28th April
Abang Azim then explained to me the type of pressure gauge that we used in the plant and its function. The C-type bourden tube pressure tube is used for measuring pressure difference. Then he also explained to me the difference between the gauge pressure, absolute pressure and atmospheric pressure.
Week 4, 27th April
The actuators that used in the plant mostly is limitorque L120 series actuators. It can be used to control butterfly, ball, and plug valves which requires 90 degrees movement.
motorized actuator
Week 4, 26th April
For the fire fighting tank and distillate tank transmitter inspection, I followed Mr. Tai, CNI technician, to take the reading for fire tank A and B from the level transmitter. Same process applied to the distillate tank.
For the turbine flow meter inspection, I followed abang Syahrul to take the flow meter reading for steam turbine. Besides that, we also checked whether it need for lubrication or not.
During the free time, Mr. Tai explained to me that AT-1000 series transmitter is designed to attach to the LT-LTC series level gauge. One of its main function is to convert the level gauge’s signal into voltage and electric current to perform tank inventory management.
AT 1000 series transmitter that attach to the LT-LTC series level gauge
Sunday, April 25, 2010
Week 3, 23rd April
For my first time, i have the chance to have a close look about the tanker and finally i know the tanker is not what i think all the time. The big tank is actually divide it into a few compartment and then i climb up top to take a look for every compartment. The sample of every compartment will be taken in which will used to determine the purity and density of it.
As the unloading process was going, i was being explained by the person in charge to know further about the machine that we will use for the whole process.
Week 3, 22nd April
Week 3, 21st April
In the evening, we had done the BOP (balance of plant) motors PM inspection. We were required to take the reading of the motor’s temperature and bearing vibration. The motors that we inspect are service water make up pump motor, demineralized water transfer pump and sea water booster pump.
Sea water booster pump motor
Demineralized water transfer pump motor
Week 3, 20th April
In the evening, I and abang Fadzli checked the transducer in the power transformer as the reading of the measurement is out of range. After a round of checking, we found out that the problem is the transducer problem. A new transducer will be replaced when the ordered transducer reached. Other that involve is Mr. Tai, control and instrumental technician.
Friday, April 23, 2010
Week 3, 19th April
In the afternoon, I and abang Razak were required to do the cathodic protection system preventative maintenance. We need to take the reading of control reference setting which is 1 connect resistance side and 1 at ground side and measure the voltage. For anode performance, it also requires to take the voltage reading which can directly take from the screen.
During the free time, I also taken the opportunity to check the steam turbine generator transformer protection relays at steam turbine generator control panel. This is the assignment given by Sri Daran. I had been ordered to check the relay whether it is in the list and at the side and the quantity must be correct too. Besides that, I also able to check the 6.6kV/415kV switchgear panels at switchgear room for steam turbine. Same process for gas turbine protection relays.
Week 2, 16th April
The 3 ventilation fan motors that haven’t install is being installed today. This time a bigger size crane is rented and the job is finished by afternoon. This time, Zulklifi and Saw, both trainees also went to the roof to observe our work.
After the lunch, a knowledge sharing session is held at the training room. Mr. Yunos, control and instrumental supervisor share his knowledge about pneumatic actuator. It is a good additional knowledge to all of us.