The PM that I did today almost same with yesterday, that is HRSG2 Siemens CEMS inspection.

Then, abang Syahrul and abang Azim explained briefly about bailey infinet and termination unit in the network system of the power plant. Every process control unit (PCU) will connect to a single termination unit (TU) and send to redundant/bailey infinet communication system. The information then will send to the operator interface station (OIS) to let the operator to control the final control element (open or close, start or stop). For amending the program of the PCU, the programmer can go to the management command system (MSC) or engineering work station (EWS).

The network system of the power plant