Abang Azmin is doing the EDG test run
Friday, June 18, 2010
Week 8, 27th May
I followed abang Azmin, patrolman to do the emergency diesel generator test run. Before the test run, the engine running hour, distillate meter reading need to take and the generator circuit breaker (52 DG) must be disconnected. After all the preparation had done, the test run begin. The test run last for about 20 minutes and accessories like exhaust temperature, lube oil level, air vessel pressure need to take after the test run. When the test run begin, the exhaust dark smoke density need to check every minute.