Friday, June 18, 2010

Week 9, 31st May

I followed abang Fadzli, patrolman to do the gas turbine auxiliaries changeover. Before the changeover begins, abang Fadzli take down the suction pressure discharge pressure abd the expansion tank level for cooling water pump. After the changeover, the readings also need to take down. The following changeover is continuing with turbine compartment ventilation fan and distillate forward pump.

Then, abang Fadzli brought us to activate online water wash to decrease the turbine temperature so that the load will increase.