For the first 3 weeks, I am assigned to electrical department. My first task is to follow Mr. Tan, an electrical technician, to check the ventilation at steam turbine control room. In the ventilation circuit breaker system, there are miniature circuit breaker, contactor, mould case circuit breaker and relay. We were required to check the on load current and insulation resistance of the circuit breaker.

Circuit breaker system

I was also given the opportunity to observe the disassemble of the circulating water pump 1A for repair. In the evening, students from Universiti Malaysia Pahang had their visit to power plant. Trainees including me follow the trip led by Mr. Sridaran.