Saturday, April 17, 2010

Week 1, 9th April

There are 2 PMs to do today, emergency diesel generator panel and fire diesel engine battery. For EDG, I and Mr. Tan do the visual inspection general cleaning and local panel battery inspection.

For diesel engine battery, we also do the same procedure. Besides that, we are required to take the reading for SG and voltage of the battery. The total voltage for a battery bank is around 24-27V.

In the evening, Mr. Sharif, supervisor of ECNI department, asked us to the control room to show how to switch on the water pump. Circuit breaker SF6 is used for 6.6kV and 415V circuit. When an accident occurred, circuit breaker is used to break the circuit.

The function of a differentiator of current is to check then three phases current is balanced or not. If it is not balance, it will sense by the current differentiator and circuit tripping will occurred.

The pump 1A is tested at the evening. Free running testing is used and after no error occurred, the connection with the shaft is connected and another testing is done. The vibration for the water pump after the repair had reduced.

Jockey pump

Diesel pump


Friday, April 16, 2010

Week 1, 8th April

Circulating water pump 1A had been left unused since November last year. Repairment had been made and the repaired shaft was installed back. All the technician from ECNI department busy with their job and i was asked to help when they needed.

In the pump hall, they also pump out the mug from the underground since it had been left unused for a long time. The installation process continue to the next day as it is a complicated system.

Week 1, 7th April

In the morning, i followed Mr. Tan to the gas turbine hall for gas turbine motor preventative maintainance (PM). In the control room, Mr. Tan explained to me that the code 88 is for motor system while code 23 is for heater system. The insulation resistance must be larger than 2M ohm and winding ohmic value must be balanced so that the system is safe.

In the evening, I followed abang Razak to circulating water pump hall to further observed their work.

Circulating water pump system description


The contractors are disassembling the pump

Week 1, 6th April

For the first 3 weeks, I am assigned to electrical department. My first task is to follow Mr. Tan, an electrical technician, to check the ventilation at steam turbine control room. In the ventilation circuit breaker system, there are miniature circuit breaker, contactor, mould case circuit breaker and relay. We were required to check the on load current and insulation resistance of the circuit breaker.

Circuit breaker system

I was also given the opportunity to observe the disassemble of the circulating water pump 1A for repair. In the evening, students from Universiti Malaysia Pahang had their visit to power plant. Trainees including me follow the trip led by Mr. Sridaran.

Week 1, 5th April

I were required to report at power plant at 8am. 4 new trainees including me were welcomed by Pn. Senah who works in Administration and Finance Department. She gave us a brief introduction about the power plant and what should we need to fulfill as a trainee during the internship period.

At 9.30am, we were asked to attend a daily meeting at the conference room. During the meeting, Mr. Suhaili, safety and security manager, briefed us about safety and precautions inside the power plant. After that, Mr. Baharim introduces us the organization by drawing out the organizational chart of this power plant.

We were told that safety boot and helmet is a must before entering the field site. We must obtain Permit to Work to start any kind of task. If we wish to enter the power plant after the working hours, permission is required. Emergency Assembly Area is where we gather when emergency alarm sounds. The area includes volleyball field as premier assembly area, and parking area which becomes the reserved one.

After the meeting, I reported to my mentor, Mr. Baharim and was given a schedule for my industrial training period. I was directed to Mr. Sridaran, ECNI engineer and he bring me to walk around the power plant to have a better understanding about the plant.

Thursday, April 1, 2010

TeNJi BuFfeT & EnD oF SeM

woohoo...finally this sem ended and i finally write something on my blog. the last time i posted is about 5 months ago...wakaka

exam time = save money time...this time realy can save a lot money coz no entertainment, no outing, no shopping...everyday at home, just spend money on daily expenses, even the patrol also can save a lot ==

but once finish exam, i decided to go to tenji since it is rm49.90 for the supper session tat start from 9.30pm-12.30am...P.S: i had hoped long enough for this tenji buffet and actually plan it before the exam finish...

in the end..only me, isaac and shengji went for the buffet..others really cant hope that much...shengji and isaac really steady, say go then sure go, wont think so much de...the way to tenji really hard as 3of us never go before...wakaka, tats y we went as early as 7.30pm and reach there about 9.00pm...i think next time no need go so early, coz it is not that hard to reach la.(with the help of GPS) ==


3 malatlou at tenji

tenji is at mount kiara...nice place, nice environment, nice night view and the most important point..NICE FOOD...and it is definitely better than jogoya...me and shengji keep say the food at there reli nice..haha...even the ice cream got 3 types..baskin31, haagan-dazz, and kindori...all are marvelous, but due to too full, i taste little bit and cant finish at all...== feel so sinful for wasting so much food T.T


all the desert at here(not include ice cream o)

Conclusion, tenji is definitely much much better than jogoya and i will go there again (if the price is right)...wakaka

Saturday, October 10, 2009

sem sem sem

erm, finally feel like post sumthing into my blog...this sem gonna end soon..wat is my wish for this sem...better result? hope can..but reality sure cant, this sem sucks..play too much...haiz...